Why Ondo is in darkness, by BEDC

Kindly Share This Story:

The management of Benin Electricity Distribution Company (BEDC Electricity Plc)  has assured residents of Ondo South of its commitment to providing power to their various communities.

This is however dependent on the Federal Government, through the Transmission Company of Nigeria (TCN), addressing the technical constraints that impede power distribution to the areas.

BEDC in its reaction to  Governor Rotimi Akeredolu’s complaint over lack of power supply to some parts of Ondo South, appealed to the governor to put pressures on TCN and other Federal Government- related agencies to create an enabling environment for BEDC to serve its customers better by addressing these technical constraints.

These constraints, according to BEDC include repair of the faulty breaker on the 30MVA TCN transformer which affected voltage to Ondo South axis causing very poor and none useful power ‘candlelight’.

BEDC also called for the replacement of the unstable Ife/Oshogbo 132KV undersized line and the recommencing/completion of the proposed 132/33KV, 2x 60MVA at Erinje in Okitipupa which will provide capacity for up to 90megawatts of power when completed.

“In order to have a lasting and complete solution to Ondo South electricity need as well as have a lasting solution to Ondo State general power limitations, the permanent solution is for TCN to complete the proposed 132/33KV, 2x60MVA at Erinje in Okitipupa project which has been awarded by NDDC and abandoned as well as replace the unstable Ife/Oshogbo 132KV undersized line” BEDC said.

When this is completed, BEDC said it will be able to take the transmitted power and distribute same to customers in other parts of Ondo South, but noted “this will only serve an additional 25% of the power needs in this area. This is because the estimated total power supply needed is 47.6MW and only additional 11MW will be available from this TCN source, hence there would still be a shortfall of about 36.6MW”.

ent Power Project (NIPP) to restore power supply to Ode-Aye town in Okitipupa and Igbokoda in Ilaje local government area of Ondo South by rehabilitating the distribution network in a phased manner and by bypassing major load using centers.

“This was done to demonstrate to customers in Ondo South axis that the network was ready to receive and distribute power when TCN makes same available” the company added.

BEDC says since 2015, it has escalated to Ondo State Government, Federal Ministry of Power and Nigerian Electricity Regulatory Commission (NERC) that the issue of power supply to major parts of Ondo South is largely and principally affected by TCN constraint.

It added: “TCN has not been able to transmit adequate power to BEDC in Ondo State and especially in part of Ondo South due to its technical constraints which has led to its existing problem of none availability of power in these locations.”

“We wish to state categorically that as a service provider, BEDC is not comfortable watching a large proportion of its customers located in Ondo state and most especially in several locations in Ondo South without supply for so many years.

The reality, however, is that in line with existing methodology of buying and transmitting bulk power from TCN grid, such power which is purchased by BEDC is what is distributed to our customers in all areas.” BEDC stated.


Kindly Share This Story:

Related Post

Leave a Reply

Your email address will not be published. Required fields are marked *

amehnews greetings

x
%d bloggers like this: